Skip to content

QINFENG Custom FIBC manufacturer since 2001

Case Study

Dewatering Bags for a Municipal Water Treatment Contractor

Twenty geotextile dewatering bags for lagoon sludge at a municipal works: produced, inspected and shipped, with the site drainage trial still ahead.

A municipal water treatment contractor was paying to haul lagoon sludge away at its full water content. The only space they had was an existing concrete pad, and the pad ends in a surface water drain they are not permitted to discharge into.

They ordered twenty geotextile dewatering bags sized for one lagoon cell: filled by pump, drained on the pad, then lifted as drained cake for disposal. The bags have been produced, inspected and shipped, and the site trial is the next step.

This record is deliberately limited to what has actually happened. Fabric specification, seams and dimensions are recorded on the batch sheet, but drainage rate, cake solids and the condition of the drained water can only be measured on the contractor’s own sludge.

Project Summary

A municipal water treatment contractor handles lagoon sludge that had to be hauled away wet, which put most of the cost into water rather than solids. They ordered dewatering bags for a trial campaign on one lagoon: fill, drain on the existing concrete pad, then lift the drained cake. The bags have shipped and are awaiting the site's drainage trial.

Project Context

Customer Type
Water treatment contractor working for a municipal authority
Country / Market
Northern Europe
Intended Use
Dewatering lagoon sludge on a concrete pad before haulage and disposal
Project Scale
Trial campaign, 20 bags, sized for one lagoon cell
Project Stage
Shipment

Challenge

The contractor was hauling lagoon sludge at its full water content, so most of every tanker load was water. They wanted to drain the material on site before haulage, but had no room for a settlement tank or a filter press, and the only available area was an existing concrete pad with a surface water drain at one end that they could not discharge into.

Risks Identified

Two risks decided the specification. First, the drained water: if the fabric released solids with the water, the drain at the pad's end would carry them off site, which is exactly what the contractor's own permit conditions forbid. Second, the drained weight: the site lifts bags with a telehandler on the loop pair, so a bag that still holds too much water cannot be lifted safely. Fine solids in the sludge also risk blinding the fabric and stopping drainage partway through the campaign.

Solution

We proposed geotextile dewatering bags sized for one lagoon cell, filled by pump through a top fill port and drained on the existing pad, with the fill port closed after each batch so rain does not re-wet the cake. The fabric opening size was selected against the fines the contractor expects in the lagoon rather than against a generic sludge figure, and the bags were laid out with the drain end of the pad bunded by the contractor so any carry-over can be seen and captured.

Why This Solution

A settlement tank or filter press was rejected by the contractor on cost and footprint, and a lined roll-off container was rejected because it would not remove any water at all. A dewatering bag does the one job the site actually needs — removing water before haulage — and it does it on the pad they already have. The fill port was specified over an open top because rain re-wetting the cake would have undone the drainage they are paying for.

Validation

Validation so far covers the order and the dispatch, not the site: fabric specification against the agreed opening size, seam stitch counts, bag dimensions and the fill port attachment are recorded on the batch sheet, and a fabric sample was retained with the batch. A trial bag with the contractor's own sludge is the next step and will be the first real measure of drainage and retention.

Confirmed Outcome

Bags produced, inspected and shipped against the confirmed specification. Drainage rate, cake solids and the condition of the drained water are not yet confirmed — they can only be measured on the contractor's own material once the trial campaign starts.

Current Status

Shipped, awaiting site drainage trial

Still To Follow Up

The trial bag result: how long drainage takes, whether the fabric blinds, and how the drained water reads against the contractor's permit conditions. Those three answers decide the fabric for any follow-on order.

Confirmed Specification

Size
Circumference 4.5 m, height 1.5 m
SWL
1,000 kg on the drained cake
Safety Factor
Confirmed with the drained weight, not the wet weight
Structure
Geotextile dewatering bag, closed flat base
Fabric
Woven geotextile, opening size agreed against the lagoon fines
Lifting Loops
Four reinforced corner loops, telehandler pick on the loop pair
Top
Top fill port, closed after each batch
Bottom
Closed flat base
Functions
Drainage on the existing concrete pad, filled by pump
Printing
None
Packing
Baled, 5 bags per bale

Project Timeline

StageDateStatusDescription
Inquiry22/09/2026CompletedContractor described the lagoon, the haulage cost problem and the pad layout with the drain at one end.
Fabric and size proposal07/03/2026CompletedFabric opening size proposed against the expected fines; bag size set from the lagoon cell volume.
Specification confirmed22/09/2026CompletedOpening size, fill port and loop arrangement confirmed in writing, with the site's lifting method noted.
Production and inspection22/09/2026CompletedBatch produced with seam and dimension checks; fabric sample retained with the batch record.
Shipment09/04/2026CompletedTwenty bags shipped in bales for the trial campaign.
Site drainage trial10/02/2026PlannedContractor fills the first bag with lagoon sludge and measures drainage, cake and drained water.

Evidence

TypeCaptionFileStage
DrawingBag dimension and fill port drawing issued for confirmation before production.Approval
Test ReportBatch sheet with fabric specification, seam stitch counts and dimensions; fabric sample retained.Production
SampleFabric sample retained with the batch, available for the contractor to compare against the trial bag.Production

Only evidence cleared for publication is listed here.

What Can Be Reused

For sludge work, the fabric has to be chosen against the fines in the material, not against a generic sludge figure, and the fill port matters more than buyers expect: a bag left open in the rain gives back part of the water it drained. The pad layout also decides the project as much as the bag does, because the drained water has to go somewhere the site is allowed to send it.

What Must Be Reconfirmed

The lagoon's fines content, which varies between cells and campaigns; the drained water route and the contractor's permit conditions; and the drained weight per bag, which sets the lifting arrangement. None of these carry over from one campaign to the next without checking.

Application Sectors

Materials